家庭裝修之龍骨施工流程以及驗收方法詳解
龍骨是用來支撐造型、固定結構的一種建筑材料。廣泛應用于賓館、候機樓。客運站、車站、劇場、商場、工廠、辦公樓、舊建筑建筑改造、室內裝修設置、頂棚等場所。龍骨是裝修的骨架和基材,使用非常普遍。下面就是一起裝修網小編給大家帶來的關于龍骨施工內容,一起去看(kan)看(kan)吧。

家庭裝修之龍骨施工流程詳解
家庭裝修之龍骨施工流程1.抄平彈線。彈線包括:標高線、頂棚造型位置線、吊掛點布局線、大中型燈位線
(1)確(que)定標高(gao)(gao)線(xian):根據室內墻上(shang)+50cm水(shui)(shui)平線(xian),用(yong)(yong)(yong)(yong)(yong)尺量至頂(ding)棚設計標高(gao)(gao),在該點(dian)畫出高(gao)(gao)度(du)(du)線(xian),用(yong)(yong)(yong)(yong)(yong)一(yi)(yi)(yi)條塑料透明軟管(guan)灌滿水(shui)(shui)后,將(jiang)軟管(guan)的(de)一(yi)(yi)(yi)端(duan)水(shui)(shui)平面(mian)(mian)對(dui)準墻面(mian)(mian)上(shang)的(de)高(gao)(gao)度(du)(du)線(xian)。再將(jiang)軟管(guan)的(de)另(ling)(ling)一(yi)(yi)(yi)端(duan)頭水(shui)(shui)平面(mian)(mian),在同側墻面(mian)(mian)找出另(ling)(ling)一(yi)(yi)(yi)點(dian),當軟管(guan)內水(shui)(shui)平面(mian)(mian)靜止時(shi),畫下該點(dian)的(de)水(shui)(shui)平面(mian)(mian)位置,再將(jiang)這(zhe)兩點(dian)連線(xian),即得吊(diao)頂(ding)高(gao)(gao)度(du)(du)水(shui)(shui)平線(xian)。用(yong)(yong)(yong)(yong)(yong)同樣(yang)方法在其(qi)它墻面(mian)(mian)做出高(gao)(gao)度(du)(du)水(shui)(shui)平線(xian)。操(cao)作時(shi)應注意,一(yi)(yi)(yi)個房(fang)間的(de)基準高(gao)(gao)度(du)(du)點(dian)只用(yong)(yong)(yong)(yong)(yong)一(yi)(yi)(yi)個,各個墻的(de)高(gao)(gao)度(du)(du)線(xian)測點(dian)共用(yong)(yong)(yong)(yong)(yong)。沿墻四(si)周彈一(yi)(yi)(yi)道墨線(xian),這(zhe)條線(xian)便(bian)是吊(diao)頂(ding)四(si)周的(de)水(shui)(shui)平線(xian),其(qi)偏差不能大于5mm。

(2)確定造(zao)型位置線(xian)(xian):對于(yu)較規(gui)則的(de)建筑空間,其吊頂造(zao)型位置可(ke)先在一個(ge)墻面量出(chu)(chu)(chu)豎向(xiang)距(ju)離,以此畫出(chu)(chu)(chu)其它(ta)墻面的(de)水平線(xian)(xian),即得吊頂位置外框線(xian)(xian),而后逐步找出(chu)(chu)(chu)各局部(bu)的(de)造(zao)型框架線(xian)(xian)。對于(yu)不規(gui)則的(de)空間畫吊頂造(zao)型線(xian)(xian),宜采用(yong)找點(dian)法,即根據(ju)施工圖(tu)紙測出(chu)(chu)(chu)造(zao)型邊(bian)緣(yuan)距(ju)墻面的(de)距(ju)離,從(cong)墻面和頂棚(peng)基層進(jin)行實測,找出(chu)(chu)(chu)吊頂造(zao)型邊(bian)框的(de)有關基本點(dian),將各點(dian)連線(xian)(xian),形成吊頂造(zao)型線(xian)(xian)。
(3)確定吊點(dian)(dian)位置:對于平頂天(tian)花,其(qi)吊點(dian)(dian)一(yi)般是(shi)按每m2布置1個,在(zai)(zai)頂棚上均勻排布。對于有疊級造型的吊頂,應注意在(zai)(zai)分(fen)層交界處布置吊點(dian)(dian),吊點(dian)(dian)間距0.8~1.2m,較大的燈(deng)具應安排單獨吊點(dian)(dian)來吊掛(gua)。

家庭裝修之龍骨施工流程2.木龍骨處理
對吊頂用的木龍(long)骨進行篩選(xuan),將(jiang)其中(zhong)腐蝕部(bu)分、斜口(kou)開裂、蟲蛀等(deng)部(bu)分剔(ti)除。對工程中(zhong)所用的木龍(long)骨均要進行防(fang)火(huo)(huo)處理,一(yi)般將(jiang)防(fang)火(huo)(huo)涂料(liao)涂刷或噴于木材(cai)表面,也可把木材(cai)放在防(fang)火(huo)(huo)涂料(liao)槽內浸漬。
對(dui)于直接接觸結(jie)構的木龍骨,如墻邊龍骨、梁邊龍骨、端頭(tou)伸入(ru)或(huo)接觸墻體的龍骨應預先(xian)刷(shua)(shua)防(fang)(fang)腐劑(ji)。要求(qiu)涂刷(shua)(shua)的防(fang)(fang)腐劑(ji)具有防(fang)(fang)潮、防(fang)(fang)蛀、防(fang)(fang)腐朽的功效。

家庭裝修之龍骨施工流程3.安裝吊桿
(1)吊(diao)桿固定件的設置方法(fa)
①用M8或M10膨脹(zhang)螺(luo)栓(shuan)將∠25×3或∠30×3角鐵固(gu)定在(zai)現澆(jiao)樓(lou)板底面上。對于(yu)M8膨脹(zhang)螺(luo)栓(shuan)要(yao)求鉆孔(kong)深(shen)度≥50mm,鉆孔(kong)直徑(jing)10.5mm為宜;對于(yu)M10膨脹(zhang)螺(luo)栓(shuan)要(yao)求鉆孔(kong)深(shen)度≥60mm,鉆孔(kong)直徑(jing)13mm為宜。
②用φ5以上高強射釘將∠40×4角鋼(gang)或鋼(gang)板(ban)等固定在現澆樓板(ban)的底面上。
③在澆灌樓面(mian)或(huo)屋面(mian)板時,在吊(diao)桿布置位置的板底預(yu)埋(mai)鐵(tie)(tie)件,鐵(tie)(tie)件選用(yong)δ=6mm厚鋼(gang)板,錨爪(zhua)用(yong)4φ8L≥150mm。
④現澆樓板(ban)(ban)(ban)(ban)澆筑前或預制(zhi)板(ban)(ban)(ban)(ban)灌縫前預埋φ10鋼筋(jin)(jin)。(對(dui)于不上人(ren)屋面,吊筋(jin)(jin)規(gui)格(ge)可(ke)選(xuan)φ6或φ8)要求預埋位(wei)置(zhi)準確,若為現澆樓板(ban)(ban)(ban)(ban)時(shi),應在(zai)模(mo)(mo)板(ban)(ban)(ban)(ban)面上彈(dan)線(xian)標示出準確位(wei)置(zhi),然后(hou)在(zai)模(mo)(mo)板(ban)(ban)(ban)(ban)上鉆(zhan)孔(kong)預埋吊筋(jin)(jin)。對(dui)于鋼模(mo)(mo)板(ban)(ban)(ban)(ban)也(ye)可(ke)先將吊桿連(lian)接筋(jin)(jin)預彎90°后(hou)緊(jin)貼模(mo)(mo)板(ban)(ban)(ban)(ban)面埋設,待拆模(mo)(mo)后(hou)剔出。

以(yi)上(shang)前兩種方式固定吊(diao)桿連接件的方法不適(shi)應于(yu)上(shang)人屋面。
(2)吊桿的連接
對于木龍骨吊(diao)(diao)頂,吊(diao)(diao)桿與(yu)主(zhu)龍骨的連接(jie)通(tong)常采用主(zhu)龍骨鉆(zhan)孔(kong),吊(diao)(diao)桿下部(bu)(bu)套(tao)絲,穿過主(zhu)龍骨用螺母緊固(gu)(gu)。吊(diao)(diao)桿的上(shang)(shang)部(bu)(bu)與(yu)吊(diao)(diao)桿固(gu)(gu)定(ding)件連接(jie)一般采用焊(han)接(jie),施焊(han)前拉通(tong)線,所有絲桿下部(bu)(bu)找平后(hou),上(shang)(shang)部(bu)(bu)再(zai)搭接(jie)焊(han)牢。吊(diao)(diao)桿與(yu)上(shang)(shang)部(bu)(bu)固(gu)(gu)定(ding)件的連接(jie)也可采用在角鋼固(gu)(gu)定(ding)件上(shang)(shang)預先鉆(zhan)孔(kong)或(huo)預埋的鋼板(ban)埋件上(shang)(shang)加(jia)焊(han)φ10鋼筋環,然(ran)后(hou)將吊(diao)(diao)桿上(shang)(shang)部(bu)(bu)穿進后(hou)彎折固(gu)(gu)定(ding)。
吊(diao)桿(gan)縱橫間距按設計要(yao)求(qiu),原則(ze)上(shang)吊(diao)桿(gan)間距應(ying)不大于1000mm;吊(diao)桿(gan)長(chang)度大于1000mm時,必須按規范要(yao)求(qiu)設置反向支撐;吊(diao)頂燈具、風(feng)口及檢修口等處應(ying)增設附加吊(diao)桿(gan)。

家庭裝修之龍骨施工驗收方法詳解
家庭裝修之龍骨施工驗收方法1、檢查木龍骨質量
使用的木龍骨(gu)(gu)應(ying)無節(jie)疤,節(jie)眼(yan)不能大于截(jie)(jie)面(mian)的1/3。水(shui)平木龍骨(gu)(gu)截(jie)(jie)面(mian)尺(chi)寸應(ying)該(gai)達到要求,小面(mian)積(ji)吊頂(ding)25*30mm,大面(mian)積(ji)吊頂(ding)25*35mm。
家庭裝修之龍骨施工驗收方法2、看龍骨是否做了防火處理
吊頂(ding)的木龍骨必須進行防火阻燃處理。應(ying)該在安裝前(qian)涂(tu)(tu)刷防火涂(tu)(tu)料,涂(tu)(tu)料必須滿涂(tu)(tu)覆蓋木質,眼觀無木質外露。涂(tu)(tu)料厚(hou)度、涂(tu)(tu)刷方法應(ying)符合相應(ying)涂(tu)(tu)料使用(yong)說(shuo)明的要求。

家庭裝修之龍骨施工驗收方法3、檢查龍骨間距
主龍(long)骨間距不(bu)(bu)大于(yu)(yu)300mm,次(ci)龍(long)骨間距不(bu)(bu)大于(yu)(yu)400mm,懸臂式龍(long)骨的(de)挑(tiao)出長度不(bu)(bu)宜大于(yu)(yu)150mm,有特殊設計要(yao)求(qiu)的(de)應依據設計要(yao)求(qiu)處理,但須進行加固。
家庭裝修之龍骨施工驗收方法4、檢查安裝是否牢固
木龍(long)骨(gu)安(an)裝需牢固,骨(gu)架排列應(ying)整齊(qi)順直,搭接(jie)處無明顯(xian)錯臺、錯位。木龍(long)骨(gu)吊(diao)桿間距不應(ying)大(da)于600mm,且在橫向龍(long)骨(gu)的兩側對(dui)稱配置(zhi),水(shui)平木龍(long)骨(gu)與罩面(mian)板接(jie)觸的一面(mian)必須創平,次龍(long)骨(gu)在接(jie)處對(dui)接(jie)錯位偏差不應(ying)大(da)于2mm。

關(guan)于龍(long)骨施工的相關(guan)信息一(yi)起裝(zhuang)修網(wang)小(xiao)編就為(wei)大家介(jie)紹(shao)到這(zhe)里了,希望這(zhe)篇文(wen)章對您有所(suo)幫助。如果您對于龍(long)骨施工還有什么不明白的地(di)方可以關(guan)注一(yi)起裝(zhuang)修網(wang),我(wo)們會盡快為(wei)您解答。